Which tonnes count as production in a CBAM verification?

Only goods that meet the specification for sale, or go on to another process, and only those under the CN codes of that production process. Off-spec goods, scrap and waste are left out, and so is packaging material, although emissions from a packaging step such as shrink foiling stay in.

Why the divisor gets checked

Your figure per tonne is the process's emissions divided by its production, which the rules call the activity level. Count tonnes that should not be there and the figure per tonne drops, which understates what your buyer declares. The verifier checks this line as closely as the fuel figures.

Counted and left out

Tonnes, clinker or nitrogen

For most goods the unit is tonnes produced under the same 8-digit CN code. Cement, other than aluminous cement, is counted in tonnes of clinker contained in it. Fertilisers are counted in kilograms of nitrogen. Convert with your clinker-to-cement ratio or kilograms of nitrogen per tonne of product, and write the conversion into your monitoring plan.

Inside the calendar year

The verifier also confirms the goods were produced between 1 January and 31 December. It may accept a cut-off up to one or two working days off 31 December, such as 30 December at 18:00, if you fix that time, measure production and stocks as close to it as you reasonably can, document it, and start next year from the same point.

Records that make this easy to check

Counting rejects and scrap by mistake

Example figures. An error this size alone would have to be corrected before a positive statement.

What Senseible does here

Senseible keeps production by CN code next to the fuel and power records for the same period, so the tonnes behind your figure are visible to anyone checking them. We build it from your records, check every figure in-house, and an accredited verifier we partner with signs it off. Have your own verifier? Send it to them.

Sources: European Commission, Guidance on CBAM verification and accreditation (24 August 2026), sections 2.2.2, 6.2 and 7.7 (with footnote 103)

Last reviewed 2026-10-31.