What checklist does a CBAM verifier use on our monitoring plan?

The Commission gives verifiers an example checklist, not a fixed form. It asks whether your plan draws the installation boundary, covers every source stream, stockpile and tank, uses the best available data sources, puts every CN code in exactly one production process, and has written procedures for new products, supplier verification reports, lab work and calibration.

Two questions behind every line

  1. Is this part of the plan allowed by the Methodology Act and the CBAM Regulation? A method the Act does not permit, a variable with no monitoring method, or the wrong functional unit fails here.
  2. Does it only meet the minimum, or is a better method available? The verifier looks for improvements you could make with equipment you already have, and for longer-term ones that would make your data more accurate.

Boundaries and the plant description

Source streams and data sources

Goods, CN codes and production processes

Suppliers, precursors, heat and electricity

Lab work and the control system

Having the procedure is not enough

The checklist only asks whether each item exists. The verifier also judges whether it works: whether a meter's range fits the flow it measures, whether the uncertainty you state is reasonable, whether the instrument suits its surroundings, and whether a procedure names who does what, where the original data sits and where results are stored. A procedure nobody follows on the shop floor will show up during testing.

What Senseible does here

Senseible's CBAM Suite keeps each good's CN code, production process and supplier with the invoices and logs behind them, which is much of what this checklist asks for. We build it from your records, check every figure in-house, and an accredited verifier we partner with signs it off. Have your own verifier? Send it to them.

Sources: European Commission, Guidance on CBAM verification and accreditation (24 August 2026), section 5.3