How is the carbon footprint of a battery calculated under the EU Battery Regulation?

Under Article 7 and Annex II of Regulation (EU) 2023/1542, a battery's carbon footprint is its life cycle greenhouse gas emissions, leaving out the use stage, divided by the total energy it delivers over its service life, in kg CO2e per kWh. The detailed rules wait on a delegated act not yet adopted in October 2026.

The functional unit

Annex II sets the functional unit as one kWh of total energy provided by the battery over its service life. Total energy is roughly usable energy per cycle times the number of cycles over the expected life. A long-life battery spreads the same manufacturing emissions over more kWh, so durability lowers the declared figure.

Life cycle stages that count

Electricity is where Indian plants differ

Cell formation, drying rooms and electrode coating use a lot of electricity. The delegated act will set how that electricity is modelled, including whether supplier-specific or contracted renewable power can replace the national grid mix. On the Indian grid, at 0.710 kg CO2 per kWh, this stage weighs more than in countries with cleaner grids, so a plant-level kWh record per batch or per kWh of cells made is worth building now.

What is still open

Illustrative footprint per kWh for an EV pack

Pack emissions, cycles and plant energy are illustrative. The delegated act defines how service life and total energy are set, which may differ from a simple cycle count.

What Senseible does here

Senseible gives the plant's own electricity and fuel emissions from bills, by month, which is the main production stage input you control in a battery footprint. Cell and material footprints come from your suppliers and an LCA model.

Sources: Regulation (EU) 2023/1542 (Batteries Regulation), Article 7 and Annex II, on EUR-Lex, ISO 14067:2018, Carbon footprint of products, CEA CO2 Baseline Database, version 21.0

Last reviewed 2026-10-18. Delegated act status checked 18 October 2026: not adopted. Check EUR-Lex for adoption and application dates before relying on any timeline.