Senseible

Can my factory get an IREDA loan for rooftop solar?

Rarely on its own. IREDA's rooftop solar scheme, in its financing norms updated to 1 October 2026, needs at least 5,000 kWp in one application, whether a single roof owner applies directly or an aggregator bundles many roofs. A factory roof is usually far smaller, so the realistic route is through an aggregator or installer.

The size rule, and which document to trust

IREDA's Financing Norms and Schemes, issue 35, updated up to 1 October 2026, set the minimum project capacity for its rooftop scheme for industrial, commercial and institutional roofs at 5,000 kWp. IREDA's older standalone sheet for the same scheme still says 1,000 kWp. The dated norms are the newer official document, so plan on 5,000 kWp and ask IREDA to confirm before you build a proposal around the lower figure.

Two ways in

What an aggregator will ask you for

  1. The legal document showing you own the roof, or your lease.
  2. A roof lease that gives the system owner and IREDA free access for the loan period, and no termination during it except for force majeure or performance, or a termination payment at least equal to the loan outstanding.
  3. Structural load, seismic and wind load reports from an engineer empanelled with your local authority.
  4. A no-objection letter from any lender that already holds a charge on your building.
  5. Twelve months of electricity bills, to size the plant against what you actually use.

The loan the aggregator gets

A 200 kW factory roof against the 5,000 kWp rule

Use the installer's site estimate for yield. On its own, a roof this size is a bank, SIDBI or installer-financed project; inside an aggregator's portfolio it can be IREDA-financed.

What Senseible does here

Whoever finances the plant, the sizing and the lender's performance check start from your bills. Senseible reads them into monthly units and CO2, the figures an installer and lender use to size the plant and confirm the saving, and its green loan check shows what else they will ask for. Senseible does not lend.

Sources: IREDA, Financing Norms and Schemes, issue 35, updated up to 01.10.2026, chapter IX Loan Scheme for Financing Rooftop Solar PV (5,000 kWp minimum, 20 kWp sub-projects, 70 to 75% loan, 10 years plus 12 months moratorium), IREDA, Loan products FAQ: IREDA is a financial institution and does not provide any subsidy, CEA, CO2 Baseline Database for the Indian Power Sector, version 22.0: 0.675 kg CO2 per kWh for FY 2025-26

Last reviewed 2026-10-29. Scheme terms change; re-check IREDA's latest Financing Norms on ireda.in every quarter, especially the rooftop minimum capacity.