Does a factory efficiency project need an environmental and social risk assessment for Verra?

Yes. Before the project start date, Verra requires a documented environmental, social and governance risk assessment, with mitigation measures sized to each risk. You then carry those measures out, keep monitoring the risks, and update the assessment at every verification.

What it must do

After the start date

At each verification

You update the assessment to report changes to the risks, including new ones, and how the measures were carried out, including any actual negative impacts.

How big it needs to be

The assessment is sized to the risk. The Standard's safeguards cover areas such as forced and child labour, contracted workers, worker training and corruption. A small efficiency retrofit can have a short list, but the document must exist before the start date.

Example: three lines from a furnace retrofit register

An example of the format only. Your own risks decide the list.

What Senseible does here

Senseible does not run risk assessments. It keeps the dated records your project produces, so the monitoring side of the assessment has documents behind it. It does not register projects or issue credits; Verra and your validation and verification body do.

Sources: Verra, VCS Standard v5.0 (16 December 2025), section 3.18, requirements 3.18.1 to 3.18.3

Last reviewed 2026-11-04. Section numbers are from VCS Standard v5.0; re-check them when Verra publishes a new version.