What does a CBAM verifier check at an Indian cement or clinker plant?

Kiln fuels and raw meal calcination, discarded bypass or kiln dust, grey versus white clinker, the clinker content of each cement checked against your customers' orders, proof behind any zero-rated biomass, and electricity, which counts for cement. The verifier must be accredited for scope I together with LII, indirect emissions.

Confirm the verifier's scope before anything else

Clinker, cement, aluminous cement and calcined clay sit in CBAM accreditation scope I. Because electricity counts for these goods, a verifier cannot hold scope I without scope LII, indirect emissions. A firm accredited only for steel or aluminium cannot sign your report.

Kiln and raw mill

Alternative fuels and biomass

Biomass burnt in the kiln is zero-rated only if it meets the EU renewable energy directive (RED II) criteria. The verifier looks for a written procedure and proofs of sustainability from a certification scheme the Commission recognises. Without them, the CO2 from rice husk, agro-waste or the biomass share of RDF is counted, not zero-rated. The fossil share of RDF, such as plastic, always counts.

Clinker type and clinker content

Electricity: grid, captive or WHR

Grid power for kiln fans and mills is counted at the default factor. To use your own captive plant's or waste heat power's actual figure, the verifier needs a single line diagram showing the direct technical link, and smart meter data at least hourly for both production and delivery.

Worked example: the clinker balance a verifier reruns at a grinding unit

Example tonnages. Clinker received from your own kiln or another plant also needs its own verified figure or the default.

What Senseible does here

Senseible reads coal, pet coke, alternative fuel and power invoices into dated records, and its CBAM Suite builds them into a verifier-ready file, checked in-house line by line. The verification is done by an accredited verifier, Senseible's partner or one you appoint.

Sources: European Commission, Guidance on CBAM verification and accreditation (24 August 2026), sections 2.4.2 (Table 4), 5.3, 7.5, 7.7, 9.2.3 and 9.2.4 (Table 11), European Commission, CBAM Guidance No. 5a, cement (14 August 2026), sections 2 and 3.1, Table 3-1

Last reviewed 2026-10-30.