Beyond fuel and meter data, a CBAM verifier at a steel plant checks your production route and steel grade, how products are grouped into processes, the alloy and scrap figures sent to importers, the precursor mass balance with heat numbers, waste gases and the year-end cut-off. It must hold scope V, VIII or both.

At the weighbridge and stockyard

In the melt shop and rolling mill

In the lab and dispatch office

What it does not check for steel

Grid electricity for steel goods is not counted in embedded emissions, except for sintered ore. The verifier still sees your power bills when checking the energy balance, but you will not be asked for a power emission factor for TMT bars or HR coil.

Worked example: the precursor mass balance a verifier reruns for bought sponge iron, 2027

Example tonnages. A gap between the two sides is a finding the verifier will ask you to explain.

What Senseible does here

Senseible reads coal, power, fuel and freight invoices into dated, fingerprinted records, and its CBAM Suite carries them into production processes by CN code with your precursors, so the mass balance and the sector figures sit in one export for the verifier. Senseible checks that export in-house; the CBAM verification itself is done by an accredited verifier, either Senseible's partner or your own.

Sources: European Commission, Guidance on CBAM verification and accreditation (24 August 2026), sections 2.4.2 (Table 4), 5.3, 7.2, 7.4.1, 7.7 and 9.2.4 (Table 11), European Commission, CBAM Guidance No. 5d, iron and steel (sections 3.1 and Table 3-1)

Last reviewed 2026-10-29.