How much power does a VFD save on a ceramic grinding machine?

About 15% of the grinding section's power in BEE's Morbi report: 66,047 kWh a year on a wall tile plant whose ball mills and blungers use 440,310 kWh. That is about 45 t CO2 on today's grid. Cost Rs 4.64 lakh, saving Rs 2.54 lakh a year, payback 1.82 years at 2010 prices.

Why grinding motors overspend

A ball mill or blunger batch runs 5 to 6 hours for body slip and 12 to 14 hours for glaze. The motor needs full speed at the start, but its load falls as the slurry evens out, and it keeps turning at full speed anyway. In the audited plant, blunger motors of 7.5 kW drew between 35% and 77% of rating, with efficiency falling from about 80% to 64% at the light end.

What the VFD does

The plant in the report

Prove it on one mill first

The 15% is a cluster rule of thumb, not a measurement on this plant. Put an energy meter on one mill, log kWh per batch for two weeks, fit the drive, and log the same batch recipe again. Check the residue on sieve too: slower running can stretch the batch, which eats the saving.

One wall tile plant, one year (estimate)

CO2 at CEA's FY 2025-26 grid factor of 0.675 kg per kWh.

What Senseible does here

Senseible reads monthly electricity bills into kWh and CO2 records tied to each bill. Pair them with a meter on the grinding feeder and the saving from the drives is easy to show a lender or buyer.

Sources: BEE, Detailed project report: variable frequency drives on grinding machine, Morbi ceramic cluster (SAMEEEKSHA), CEA CO2 Baseline Database, version 22.0

Last reviewed 2026-11-01. Report figures are from a BEE SME programme project report; costs and paybacks are at the report year's prices. Check today's tariff and a current drive quote.