In Frontier's published offtake template, the buyer pays only when credits are delivered, meaning issued by the credit issuer and received by the buyer. Before that, milestones gate the deal: conditions precedent set the commencement date, then construction reaches a commercial operation date. Miss them without a fix and the buyer can walk away.

The milestone sequence

  1. Effective date: the contract is signed.
  2. Conditions precedent: project-specific items the buyer must approve, such as permits, a technical milestone, and an approved protocol and credit issuer.
  3. Commencement date: all conditions met. From here the buyer is committed to pay for credits delivered to spec.
  4. Financial close: lenders usually fund after commencement.
  5. Commercial operation date: the facility is built and can deliver.
  6. Delivery: the buyer receives the supplier's certification and the issued credits. Payment follows each delivery.

If the project slips

Other terms to read

Prepurchase is different

A prepurchase pays upfront, before tonnes exist. Frontier uses it for early-stage teams; offtakes pay on delivery.

What Senseible does here

Forward contract and milestone tracking is one of Senseible's carbon removal capabilities: each milestone and delivery sits next to the batches and verifier evidence pack behind it, so both sides see what is due.

Sources: Frontier, Publishing Frontier's offtake agreement template (15 August 2024), Frontier, Apply for offtake: evaluation lenses, diligence steps and contracting

Last reviewed 2026-11-02.