Which parts of a cement plant are inside the European Union (EU) Carbon Border Adjustment Mechanism (CBAM) boundary, from the raw mill to the bagging plant?

The Commission's cement guide puts inside the boundary raw material grinding, fuel preparation, the kiln and cooler, clinker storage under cover, cement grinding, storage, packaging, dispatch and emissions control. Equipment unrelated to cement production, and the purchase and upkeep of infrastructure and equipment, are outside.

A conveyor belt from rock to bag

A cement plant is one long belt: crush and grind the raw mix, burn it into clinker, grind clinker with additives into cement, bag it. CBAM is the EU's charge on the carbon built into imported goods. The guide says which stretches of that belt belong to the figure.

Clinker side, inside the boundary

Cement side, inside the boundary

Outside

Electricity is inside

Cement is not on the list where only direct emissions count, so electricity used by the kiln system and the cement mill is reported separately and counted, with their direct emissions.

Electricity by area at one plant in a year (example)

Meter readings are example numbers. Whether a given load is unrelated to cement production is for your verifier to confirm.

What Senseible does here

Senseible reads fuel invoices and electricity bills into monthly records. Sub-metering your plant is custom, on request, so until then the split by area comes from your own meters. Senseible builds the verifier-ready file and checks every figure in-house; an accredited verifier Senseible partners with signs it off, or the client sends it to their own.

Sources: European Commission, CBAM Guidance No. 5a, cement (14 August 2026)

Last reviewed 2026-11-07. Check sections 2.2.3 and 3.2 of the guide against Annex I, points 3.3 and 3.4 of Implementing Regulation (EU) 2025/2547. The guide says it is not legally binding.