Who is on a CBAM verification team that visits our plant?

At least one CBAM lead auditor, who directs the work and signs the statement. CBAM auditors and technical experts join where your plant needs them, for example for continuous emission monitoring or a disputed CN code. A separate independent reviewer checks the file before it is issued and is never part of the team.

The lead auditor runs the engagement

Every CBAM verification is carried out under the responsibility and direction of one CBAM lead auditor. This is a senior person, authorised to sign verification statements for the verification firm, and required to communicate effectively in English. A team can be just this one person, but then the lead auditor must hold every competence your plant needs alone.

Put your most senior data person opposite the lead auditor. Questions about scope, findings and the timeline go through them.

Auditors and technical experts, if your plant calls for them

The verifier decides the team size before signing the contract and during its strategic analysis of your plant. CBAM auditors work under the lead auditor's supervision. A technical expert is brought in for one subject and supplies information to the team, under the lead auditor's direction.

Someone who speaks your plant's language

At least one person on the team must be able to speak and write the language needed to interview your staff and explain findings. The firm may hire an interpreter instead, but stays responsible for the translation. The report itself must be in English.

The reviewer you will not meet

After the team drafts its report, an independent reviewer at the verification firm checks the team's competence, the risk analysis, the evidence and the opinion. This person must not be on the team or do any verification work for your installation. If the reviewer sends the file back, the lead auditor fixes it and the changes are reviewed again, so allow time for this before your buyer's deadline.

Extra faces on site

People kept off your team

What Senseible does here

A small team gets through your plant faster when every figure already points to its bill, meter reading or lab report. Senseible's CBAM Suite keeps that trail for each line of your operator report. We build it from your records, check every figure in-house, and an accredited verifier we partner with signs it off. Have your own verifier? Send it to them.

Sources: European Commission, Guidance on CBAM verification and accreditation (24 August 2026), sections 4.14, 8.1, 8.2, 9.2.1 and 9.3.1, Table 5, Annexes II and III

Last reviewed 2026-11-03.