Senseible

We started our energy project last year. Is it too late to register with Gold Standard?

Maybe. Gold Standard requires regular and retroactive projects to submit for preliminary review within one year of the project start date, and a retroactive project submitted later is not eligible. The start date is the earliest date you committed to spending on implementation, such as signing the equipment contract, not commissioning.

Find your real start date first

Regular or retroactive

If the first round of stakeholder consultation happened before the start date, the project is regular. If it happens after, the project is retroactive. Both face the same one-year limit for the first submission. A retroactive project must also hold at least a physical stakeholder meeting before it submits, and explain why consultation came late.

What you can still credit

Adding equipment later works the same way

A certified project that adds a new technology or measure must request a design change within one year of that component's start date. Miss it and that component cannot be certified.

Example: a biomass boiler project

Dates are an example.

What Senseible does here

Senseible keeps your fuel and electricity invoices dated and fingerprinted from the first bill, which helps show the baseline and the start date to a VVB. It is not a Gold Standard developer or auditor.

Sources: Gold Standard, Principles & Requirements v2.1: 4.1.35, 4.1.39 to 4.1.42, 4.1.49, 5.1.37 and 5.1.51, Gold Standard, Stakeholder Consultation and Engagement Requirements v2.1 (14 June 2022)

Last reviewed 2026-11-03. Principles & Requirements v2.1 (published 31 January 2025) listed a planned update for 5 December 2025; check Gold Standard for a newer version before relying on these timelines.