What stakeholder meeting does Gold Standard require before we list our project?

At least two rounds: one mandatory physical meeting with local stakeholders and a feedback round of at least 30 days. Invite people at least 30 days before the meeting, share a non-technical summary at least a week ahead, and hold the first round before the project start date, or the project becomes retroactive.

Who must be invited

Before the meeting

At the meeting and after

Retroactive projects and the report

If consultation happens after the start date, hold at least the physical meeting before submitting for preliminary review; it may be combined with the feedback round. Preliminary review takes a draft report on the first round. The full report on both rounds is due within one year of the project start date.

Example: a consultation timeline

Dates are an example.

What Senseible does here

For farm projects, Senseible's offline field app records each farmer's consent in person, with when, how and by whom it was given. It does not run or document Gold Standard consultations.

Sources: Gold Standard, Stakeholder Consultation and Engagement Requirements v2.1 (14 June 2022), Gold Standard, Principles & Requirements v2.1: 4.1.35 and 5.1.1