What did the November 2021 order require of pumped storage and battery projects to get the inter-state transmission system waiver?

The Ministry of Power order of 23 November 2021 gave pumped storage plants and battery energy storage systems commissioned up to 30 June 2025 the inter-state transmission system (ISTS) waiver if at least 51% of their annual pumping or charging electricity came from solar or wind. It ran 25 years for pumped storage and 12 years for batteries.

The conditions in the 23 November 2021 order

What later orders changed

Our reading of how they fit

The 2025 order says it partly amends the earlier orders. For a battery that is not co-located, it points back to the earlier orders, which on our reading means the 2021 taper and 12 years still apply. The 2025 order does not spell this out, so confirm it before you rely on it.

The 51% charging test for a battery

The volumes are an example. The 51% test is the 2021 order's.

What Senseible does here

Senseible reads your electricity bills and fuel invoices into dated records, so the units on your bills are on file. It does not read transmission orders or tell you which waiver band a project falls in; that comes from the developer's commissioning and award dates.

Sources: Ministry of Power, orders on waiver of inter-state transmission charges, 2020 to 2025 (compiled PDF)

Last reviewed 2026-11-06. Read from the image pages of the 23 November 2021 order and the 10 June 2025 order, and the text of the 29 May 2023 order, in the compiled PDF, on 6 November 2026. The 2021 conditions may have been changed by later orders; the reading of how the 2025 order fits is marked as our own.