We added no new equipment this year. Can we still verify our Verra project?

Yes. For each verification period you must show that project activities were carried out as designed. Where you added nothing new, you show that the activities you installed earlier kept running. New equipment is not a condition for verifying.

What the rule asks

What 'kept running' looks like in a factory

What to watch

Example: a year with no new equipment

An example of the evidence set. Your monitoring plan lists the exact records.

What Senseible does here

Senseible keeps your dated monthly fuel and power invoices, which shows an earlier installation kept running year after year. It does not register projects or issue credits; Verra and your validation and verification body do.

Sources: Verra, VCS Standard v5.0 (16 December 2025), section 3.1.10

Last reviewed 2026-11-04. Section numbers are from VCS Standard v5.0; re-check them when Verra publishes a new version.