Does placing the equipment order set the Verra project start date?

Yes, it can. For energy and industry projects, Verra's VCS Standard v5.0 gives signing a contract to buy equipment, or beginning construction, as examples of the first significant action that sets the project start date. The crediting period starts later, at commercial or functional operation. Research pilots and required stakeholder work do not set it.

Two dates, two jobs

What does not set the start date

Why the order date matters

Several steps must be finished before the project start date, not after. The standard asks for the stakeholder engagement work, the environmental, social and governance risk assessment and the right to operate to be in place by then. If an order is signed first, those dates are already behind you.

Example: furnace project dates (example dates)

Example dates. The listing and registration deadlines count from the crediting period start, as in VCS Standard v5.0 Section 3.8.

What Senseible does here

Senseible keeps dated invoices and bills, so the order, the delivery and the first months of fuel and power use after switch-on each have a date on file. Setting the start date is for the project design and the verifier; credits come only from the registry.

Sources: Verra, VCS Standard v5.0 (16 December 2025), Sections 3.7 and 3.8