Senseible

How does a Ballari ore beneficiation plant work out electricity carbon per tonne?

Divide the plant's metered kWh for crushing, grinding, screening and pumping by tonnes of concentrate produced, and multiply by 0.675 kg CO2 per kWh for FY 2025-26. Report per tonne of concentrate and per tonne of feed, because yield varies with ore grade.

Inputs

Why yield matters

Low grade feed means more tonnes ground per tonne of concentrate. Showing both figures explains a month where carbon per tonne rose.

Water and tailings

Pumping water and handling tailings draw power too. Meter them so savings from water recycling show up.

What Senseible does here

Senseible reads electricity bills (CEA grid factor 0.675 kg CO2 per kWh for FY 2025-26, CO2 Baseline Database version 22.0) and diesel, LPG and gas invoices (IPCC 2006 defaults) into a dated, fingerprinted Scope 1 and 2 record for each site. Intensity per unit uses the activity count you enter, and estimates are labelled as estimates.

Sources: CEA CO2 Baseline Database for the Indian Power Sector, IPCC 2006 Guidelines, Volume 2 Energy, GHG Protocol Corporate Standard

Last reviewed 2026-10-21.