Do the Ministry of Power star-label carbon dioxide (CO2) projections use the 0.675 kilograms per kilowatt hour (kWh) grid factor?

Dividing the projected savings in the Ministry of Power releases gives 0.80 to 0.86 kilograms of CO2 per kWh for most label launches and 0.72 for visi coolers, against 0.675 for the financial year (FY) 2025-26 grid. The releases do not say which factor they used, so keep national projections out of your own report.

The ratios, from the releases' own figures (units of electricity taken as kWh)

Why they differ from 0.675

The releases do not state the emission factor, the years it covers or whether it is a grid average, so I cannot say why the figures differ. A projection over a decade can use a different factor from the one for a single reporting year. These ratios are my division, not figures in the releases.

For your own report use the factor for your reporting year (0.675 kg CO2 per kWh for FY 2025-26, 0.710 for FY 2024-25) on your own metered kWh. A national projection is a policy estimate for a whole market, not a saving on your meter.

What to do instead

Measure the kWh before and after, multiply by the factor for that year, and see the linked page on project reports for the same check on cluster projects.

A freezer saving 110 kWh a year (example)

The 110 kWh is an example.

What Senseible does here

Senseible reads fuel invoices and electricity bills into monthly records, so the kilowatt hours on your bills before and after a change sit in one place.

Sources: Press Information Bureau, Ministry of Power: star rating for deep freezers and light commercial air conditioners (2 March 2020), Press Information Bureau, Ministry of Power: Bureau of Energy Efficiency 21st Foundation Day (1 March 2023), Press Information Bureau, Ministry of Power: packaged boilers and visi coolers programmes (1 March 2024)

Last reviewed 2026-11-05. Projected savings are from the Press Information Bureau releases of 2 March 2020, 1 March 2023 and 1 March 2024. The kg per kWh ratios are my own division and are labelled as such. The releases do not state the factor behind them. The same check on cluster project reports is on the linked live page, and this page covers only the Ministry of Power star-label projections.