When must a CCTS obligated plant submit its monitoring plan, and what goes in it?

Within three months of the start of the first trajectory period, then every year within three months of the compliance year starting. BEE reviews and approves it. It lists emission sources and source streams, meters and sampling points, methods, activity data sources, data flow controls and who is responsible.

Deadlines

Minimum contents (Section 5.6)

BEE's template

BEE publishes an Excel-based template that walks through seven steps: set the gate-to-gate boundary, list activities and sources, identify source streams, set methods, write procedures, review, and keep it updated.

What Senseible does here

Senseible keeps a plant's fuel and electricity invoices as dated, fingerprinted monthly records, the activity data its monitoring plan and verifier work from.

Sources: BEE, Detailed Procedure for Compliance Mechanism under CCTS, BEE, Monitoring Plan Template under Compliance Mechanism (instructions)