Senseible

Do UPS losses count in a data centre's Scope 2?

Yes, they are already inside your metered electricity. A double conversion UPS loses a few percent of what passes through it as heat, which then also needs cooling. The losses do not need a separate line in Scope 2, but they show up in PUE and in what you allocate to customers.

Where the losses go

Cutting them

What Senseible does here

Senseible reads each site's monthly electricity bills into a dated Scope 2 record, keeps renewable purchase documents beside them for market based reporting, and records diesel for backup generators as Scope 1. Grid factors outside India are entered from the official source and labelled. Customer shares use the allocation key you enter.

Sources: GHG Protocol Scope 2 Guidance, ISO (ISO 14067, ISO/IEC 30134)

Last reviewed 2026-10-21.