Senseible

What charges do I pay on green energy open access power: wheeling, cross-subsidy surcharge, additional surcharge and banking?

On green open access power you pay the generator's tariff plus transmission and wheeling charges, losses deducted in units, the cross-subsidy surcharge, an additional surcharge unless you already pay the discom's fixed charges, and a banking charge on units you bank. Your state commission sets each value, usually in its yearly tariff order.

The charges and who sets them

The Green Energy Open Access Rules, 2022 set the national framework. The rupee value of every line comes from your state electricity regulatory commission's open access regulations and tariff orders.

What the 2022 Rules cap

Losses change the real price per unit

Losses are taken in kind, so your PPA tariff is paid on injected units but you receive fewer. Divide the tariff by the share of units that arrive. At ₹3.60 per kWh and 8% losses, each unit delivered costs 3.60 / 0.92 = ₹3.91 before any other charge.

Inter-state plants also depend on the Ministry of Power's waiver of inter-state transmission charges for solar and wind, which was full for plants commissioned by 30 June 2025. Plants commissioned from 1 July 2025 pay 25% of the charges in the first year band, 50% in the second and 75% in the third, and full charges from 1 July 2028. Ask the developer which band the plant you are contracting falls in.

Comparing with the discom's green tariff

The same Rules let discoms offer a green tariff: the average cost of renewable power the discom buys, plus the cross-subsidy surcharge and a service charge, as fixed by the state commission. It needs no PPA, no scheduling and no banking. Compare the landed open access cost per delivered kWh against the green tariff premium on your bill, for the same months and the same load profile.

Worked example: landed cost per delivered kWh (illustrative rates)

Every rate here is assumed for the arithmetic. Take the real values from your state commission's current order and the developer's offer.

What Senseible does here

Senseible reads open access units on your HT bill as billed units and keeps them separate from discom units, so location-based and market-based Scope 2 can both be traced. The market-based claim needs the generator's attribute evidence, which you record against those units.

Sources: Electricity (Promoting Renewable Energy Through Green Energy Open Access) Rules, 2022, G.S.R. 435(E), 6 June 2022, and Amendment Rules of 27 January 2023 (Ministry of Power), Electricity Act, 2003, Section 42 (open access, cross-subsidy and additional surcharge), Ministry of Power orders on waiver of inter-state transmission charges for solar and wind, with the phase-down from 1 July 2025, GHG Protocol Scope 2 Guidance

Last reviewed 2026-10-19. Charges come from each state's open access regulations and yearly tariff order; the central Rules were last amended on 27 January 2023 and the ISTS waiver steps up each 1 July until 2028. Recheck all three before signing (checked 19 October 2026).