Are inter-state transmission system losses waived for solar and wind power, or only the charges?

Only the charges, in general. The Ministry of Power's order of 23 November 2021 says the waiver is for inter-state transmission system (ISTS) charges and not losses, with one exception: the waiver of losses applies to projects whose bidding was completed up to 15 January 2021. Earlier orders had waived charges and losses together.

What the orders say

How to read it for a contract

If the bid for your supplier's project closed on or before 15 January 2021, ask whether the project is in the exception. If it closed later, the order does not waive losses for it.

The general rule after the November 2021 order is that inter-state losses are still applied to your scheduled energy. The exception is for projects whose bidding was completed up to 15 January 2021, which the order names.

What the exception changes, with an assumed loss

The 3 percent is not a measured loss. Use your supplier's scheduling statements for the real figure.

What Senseible does here

Senseible reads your electricity bills and fuel invoices into dated records, so the units on your bills are on file. It does not read transmission orders or tell you which projects are in the exception; that comes from the date the supplier's bidding was completed.

Sources: Ministry of Power, orders on waiver of inter-state transmission charges, 2020 to 2025 (compiled PDF)

Last reviewed 2026-11-06. Read from the Ministry of Power orders of 5 August 2020, 15 January 2021, 23 November 2021, 1 December 2022 and 29 May 2023 in the compiled PDF, on 6 November 2026. The loss percentage in the example is assumed.