Which wind and hydro projects count towards the wind and hydro components of the Renewable Consumption Obligation?

Under Ministry of Power notification S.O. 4421(E) of 27 September 2025, the wind and hydro components of the Renewable Consumption Obligation (RCO) are met from projects commissioned after 31 March 2024. Older hydro sits in other renewable energy, which also lists all wind. The wind, hydro and other components can cover each other's shortfalls.

What the notes to the table say

Who this matters to

The targets page explains who carries which part of the obligation, for a distribution company and for a factory.

Where the text is not exact

Note 5 lists all wind power projects under other renewable energy without repeating a date, while Note 2 reserves the wind component for projects commissioned after 31 March 2024. Our reading is that older wind belongs in the other component and newer wind in the wind component; the notification does not say it in those words.

Note 3 says free power from "such projects" can meet the hydro component. On our reading, "such projects" means those commissioned after 31 March 2024. Note 5 puts free power from hydro commissioned before 1 April 2024 into other renewable energy.

2026-27 shares for a distribution company with 10,000 million units of adjusted consumption

The 10,000 million units is an example. The percentages and the fungibility rule are the notification's.

What Senseible does here

Senseible reads your electricity bills and fuel invoices into dated records, so the units on your bills are on file. It does not work out an obligation or tell you which component a unit counts under.

Sources: Ministry of Power, S.O. 4421(E), 27 September 2025, minimum share of renewable electricity for designated consumers

Last reviewed 2026-11-06. Read from Notes 2, 3 and 5 and paragraphs 3 and 5 of S.O. 4421(E), 27 September 2025, on 6 November 2026. The two readings in the section on exactness are our own and are marked as such.