How does the Ministry of New and Renewable Energy specification size a raised solar structure as its height above the roof increases?

The Ministry of New and Renewable Energy (MNRE) specification sets four classes of raised structure by clearance from the roof, all marked for reference only: up to 1,000 millimetres, 1,000 to 2,000, 2,000 to 3,000 and over 3,000. Base plate thickness rises from 5 to 6, 8 and 10 millimetres across them.

The four classes (for reference only)

These are clauses from the technical specification in Annexure 3 of MNRE's guidelines for its residential rooftop solar scheme, Pradhan Mantri Surya Ghar: Muft Bijli Yojana. A factory is not bound by them, but they are a published checklist to hold a quotation against.

Rules common to all four

Clearance numbers that do not match

The specification gives different clearances in different places. The 600 mm and 8 feet figures come from the opening paragraphs of Annexure 3, not from the structure clauses. The components paragraph asks for module mounting structures of minimum 600 mm ground clearance at the lowest point from the roof surface. The ballast clause allows 70 to 150 mm and the tin shed clause asks for more than 100 mm. The raised-structure classes are all marked for reference only. Another line says an elevated structure must have a minimum ground clearance of 8 feet at the lowest point to be eligible for the residential subsidy. Settle which applies in your quotation and have the drawing state it.

A structure 3.2 metres above the roof (example)

The height and leg spacing are examples. The dimensions are from the specification.

What Senseible does here

Senseible reads fuel invoices and electricity bills into monthly records, so the grid units you buy each month are on file before and after the plant goes live. It does not design or check structures.

Sources: Ministry of New and Renewable Energy (MNRE), Guidelines for PM-Surya Ghar: Muft Bijli Yojana, Central Financial Assistance to Residential Consumers, with Annexures 2 to 4