What does the Ministry of New and Renewable Energy specification say about fixing rooftop solar on a tin shed factory roof?

For tin sheds, the Ministry of New and Renewable Energy (MNRE) specification asks for a structure designed to the shed's slope, parallel to the shed or at the shed's tilt, with its lowest point more than 100 millimetres (mm) above the sheet, a base riveted to the purlin, and every structure member at least 2 mm thick.

The tin shed clauses

These are clauses from the technical specification in Annexure 3 of MNRE's guidelines for its residential rooftop solar scheme, Pradhan Mantri Surya Ghar: Muft Bijli Yojana. A factory is not bound by them, but they are a published checklist to hold a quotation against.

Rules that sit beside them

What the specification does not tell you

It sets no load limit for sheets and purlins and says nothing about corrosion of an old sheet. Ask the vendor for a written roof strength check by a structural engineer before you sign. My reading: the parallel option is tied to a shed sloping in proper south direction, so for a shed sloping another way the clause leaves only the second option. Either way, ask for a yield estimate for your own slope and orientation.

Points for the quotation

What Senseible does here

Senseible reads electricity bills into monthly records, so the units you import month by month sit in one place. It does not check roofs or structures.

Sources: Ministry of New and Renewable Energy (MNRE), Guidelines for PM-Surya Ghar: Muft Bijli Yojana, Central Financial Assistance to Residential Consumers, with Annexures 2 to 4

Last reviewed 2026-11-06. Re-check clause numbers and figures against the current version of the guidelines before you rely on them. Clause numbers are from Annexure 3, section 3.12 (ii). Roof strength is for a structural engineer to confirm.