Which printed figures can you trust in the Bureau of Energy Efficiency (BEE) Odisha raw material preheating reports for 50, 100 and 200 tonne a day (TPD) sponge iron kilns?

BEE's Odisha reports preheat kiln feed with flue gas, saving 8,251, 14,145 and 30,647 tonnes of coal a year for 50, 100 and 200 tonne a day kilns. Each prints costs, coal baselines and paybacks that differ between summary, text and annexure, so check which figure you rely on.

The three reports on the annexure basis

Three project costs in each report

The payback is in years, and depends on the cost you use

The summary tables print 0.9, 1.00 and 0.83 under a "Months" heading; the text says years. On the full body costs: 181.50 / 192 = 0.95 years, 375.10 / 336 = 1.12 and 671.00 / 738 = 0.91. On the printed summary costs: 0.86, 1.12 and 0.83. The 100 TPD's printed 1.00 uses its Rs 341 lakh equipment cost. Plan on the full-cost figures, since erection and cabling are real.

The coal baselines do not agree

Carbon dioxide (CO2)

None of the three reports prints a CO2 figure. On Indian coal at 1.76 kilograms of CO2 a kilogram, the saved coal is 14,522, 24,895 and 53,939 tonnes a year, less power at the Central Electricity Authority (CEA) factor for financial year (FY) 2025-26, 0.675 kilograms a kWh: 284, 365 and 583 tonnes. That is a net of about 14,238, 24,530 and 53,356 tonnes. The coal here is rated 3,000 kilocalories a kilogram, which probably carries less carbon than India's average, so your own coal's carbon content will give a better number. Take the coal tonnes from your own ledger, not these baselines.

The 200 TPD report, rebuilt

Printed lines are the reports' own at the reports' prices (2010). The CO2 lines are our arithmetic, an estimate, using Senseible's Indian coal factor and the CEA version 22.0 grid factor.

What Senseible does here

Senseible reads fuel invoices and electricity bills into monthly records, so your coal bought by month is on file to test a report's baseline against. It does not measure kiln flue gas; that comes from your own survey.

Sources: BEE, Detailed project report: raw material preheating, 50 TPD, Orissa sponge iron cluster (SAMEEEKSHA), BEE, Detailed project report: raw material preheating, 100 TPD, Orissa sponge iron cluster (SAMEEEKSHA), BEE, Detailed project report: raw material preheating, 200 TPD, Orissa sponge iron cluster (SAMEEEKSHA), Central Electricity Authority (CEA), CO2 Baseline Database for the Indian Power Sector

Last reviewed 2026-11-05. Report figures are from BEE's Small and Medium Enterprises (SME) programme project reports, with coal at Rs 2,500 a tonne and power at Rs 3.30 a kWh. Check today's prices, your own coal ledger and a current quote before you rely on any saving.